Changes to Connections Portal
Some small changes have been made to the Connections Portal for both the Application & EWR process.
Applications
Electrical Contractors will now be asked the below when submitting an application:
“I warrant the proposed connection is in accordance with the TasNetworks Service and Installation Rules and all relevant Australian Standards and Legislation.”
Remember, it is your responsibility to ensure you are familiar with the appropriate rules & legislative requirements.
EWR
To help us improve the scheduling process and clarify how many site visits will be required, we are adding a few additional questions where a Tee-Up with TasNetworks is requested,
- Do you require disconnection on one visit, and reconnection on a second visit?
- Is the disconnect/reconnect required on different days?
If you have any questions about these changes, please contact the 'Connection Services' team on 1300 137 008 and select option 2.