Final Investment Decision update - Sept 2024

To align with the revised timing of Marinus Link’s Stage 1 Final Investment Decision (FID), North West Transmission Developments (NWTD) has also adjusted the timing of its Stage 1 FID from December 2024 to May 2025.

Importantly, the revised approach does not impact NWTD’s Stage 1 construction schedule to commence in 2026, and the expected completion date of 2029 remains unchanged.

Marinus Link adjusted the timing of its Stage 1 FID for greater certainty of key project aspects, such as procurement, environmental permits and land access.