Working with landowners

TasNetworks is working to ensure project requirements are balanced with the needs of landowners and the community when determining where transmission infrastructure will be located for the North West Transmission Developments project.

Since August 2022, the placement of 42 towers have been adjusted along the proposed route as a result of engagement with landowners concerning their land use requirements such as locations of pivot irrigators. Another 20 towers have been moved due to technical findings as a result of field studies and some adjustments have also been made to the design of towers.

Investigations and consultation with landowners continues to be undertaken throughout the transmission corridors as the project progresses.

Community members can ask questions about the project any time by emailing nwtd@tasnetworks.com.au

Share Working with landowners on Facebook Share Working with landowners on Twitter Share Working with landowners on Linkedin Email Working with landowners link
<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>