• Removal of Paper-Based Application Forms - 1 July, 2026

    The TasNetworks’ Connection Portal has been in place for approximately five years to support the submission of connection applications and electrical works requests. During this time, paper-based applications via forms on our website have also been accepted.

    From 1 July, these paper-based forms will be removed and can no longer be used to submit applications. All submissions must be made through the Connection Portal.

    If you require assistance with registering for the portal or submitting an application, please contact us on 1300 137 008.

    The TasNetworks’ Connection Portal has been in place for approximately five years to support the submission of connection applications and electrical works requests. During this time, paper-based applications via forms on our website have also been accepted.

    From 1 July, these paper-based forms will be removed and can no longer be used to submit applications. All submissions must be made through the Connection Portal.

    If you require assistance with registering for the portal or submitting an application, please contact us on 1300 137 008.

  • BYDA Registration Fee – 1 July, 2026

    Following approval of the AER ringfencing waiver, TasNetworks will commence charging for Before You Dig Australia (BYDA) registrations for all connections of Private Underground Consumer Mains to TasNetworks poles from 1 July 2026. This will apply for EWRs submitted on or after this date.


    An administration fee of $59.88 (ex GST - for financial year 26/27) will apply. This fee will typically be charged via the customer’s retailer and will appear on their electricity bill.


    It is important to remember:

    • Landowner approval (eg. Council, State Growth etc.) is still required, and evidence must be submitted at the application stage.
      • In some cases, landowners may not approve these connections so ensure you obtain these approvals BEFORE commencing any work onsite.
    • The TasNetworks BYDA Template must be completed in full and submitted with the EWR once all work onsite has been completed.
      • Only the TasNetworks BYDA Template will be accepted
      • You can find examples of our BYDA information requirements here
      • TasNetworks registers the private asset from TasNetworks pole to the Boundary
    • Customers will continue to own the private consumer mains and following faults, TasNetworks will make safe as required and communicate that it will be the customer's responsibility to address any further repairs.

    Following approval of the AER ringfencing waiver, TasNetworks will commence charging for Before You Dig Australia (BYDA) registrations for all connections of Private Underground Consumer Mains to TasNetworks poles from 1 July 2026. This will apply for EWRs submitted on or after this date.


    An administration fee of $59.88 (ex GST - for financial year 26/27) will apply. This fee will typically be charged via the customer’s retailer and will appear on their electricity bill.


    It is important to remember:

    • Landowner approval (eg. Council, State Growth etc.) is still required, and evidence must be submitted at the application stage.
      • In some cases, landowners may not approve these connections so ensure you obtain these approvals BEFORE commencing any work onsite.
    • The TasNetworks BYDA Template must be completed in full and submitted with the EWR once all work onsite has been completed.
      • Only the TasNetworks BYDA Template will be accepted
      • You can find examples of our BYDA information requirements here
      • TasNetworks registers the private asset from TasNetworks pole to the Boundary
    • Customers will continue to own the private consumer mains and following faults, TasNetworks will make safe as required and communicate that it will be the customer's responsibility to address any further repairs.
  • TasNetworks is seeking industry feedback - register your interest by COB 13/03/26

    TasNetworks is seeking industry participants for an online forum to engage on TasNetworks services for the next regulatory control period, 2029-2034. This includes specific engagement on an Accredited Service Provider (ASP) scheme. Engagement will all be done online with a survey also available for those that are unable to attend.

    Please register your interest via email to revenue.reset@tasnetworks.com.au by close of business 13/03/2026. Any questions and/or comments can also be directed to the same email address.

    TasNetworks is seeking industry participants for an online forum to engage on TasNetworks services for the next regulatory control period, 2029-2034. This includes specific engagement on an Accredited Service Provider (ASP) scheme. Engagement will all be done online with a survey also available for those that are unable to attend.

    Please register your interest via email to revenue.reset@tasnetworks.com.au by close of business 13/03/2026. Any questions and/or comments can also be directed to the same email address.

  • Working near low voltage overhead insulated services

    TasNetworks has been working with WorkSafe Tasmania and reviewed the Safe Approach Distances (SAD) for 'Working near TasNetworks owned Low Voltage (LV) Overhead (OH) insulated Services'.

    All workers (and any tools in use) must keep a minimum 1-metre Safe Approach Distance (SAD) from overhead low voltage service lines.

    Please review the attached brochure as provides additional detail and also covers;

    • SAD requirements for insulated Service Lines
    • Options for scenarios where the 1 metre SAD cannot be maintained.


    *Note: This information applies only to LV service lines. SADs for overhead distributions lines are different - see the TasNetworks website for details.


    TasNetworks has been working with WorkSafe Tasmania and reviewed the Safe Approach Distances (SAD) for 'Working near TasNetworks owned Low Voltage (LV) Overhead (OH) insulated Services'.

    All workers (and any tools in use) must keep a minimum 1-metre Safe Approach Distance (SAD) from overhead low voltage service lines.

    Please review the attached brochure as provides additional detail and also covers;

    • SAD requirements for insulated Service Lines
    • Options for scenarios where the 1 metre SAD cannot be maintained.


    *Note: This information applies only to LV service lines. SADs for overhead distributions lines are different - see the TasNetworks website for details.


  • Accuracy of Connection Applications and EWR Submissions

    When submitting Applications and Electrical Works Requests (EWRs) it is important that they both accurately reflect the work that has been completed onsite.

    Correct details such as the supply type, number of phases, pole ID and maximum demand are needed to assess the connection request.

    Where our crew attend to perform the connection and find that the information provided is incorrect, the job will be incomplete, and new paperwork will be required which will result in a delay to the customers connection.

    This is particularly important for private underground consumer mains that run through road reserve / public land. If the required landowner approvals and BYDA drawings have not been provided, works will not proceed.

    For more information on this process, please refer to the current Service & Installation Rules and the Hub article from June 2025.

    When submitting Applications and Electrical Works Requests (EWRs) it is important that they both accurately reflect the work that has been completed onsite.

    Correct details such as the supply type, number of phases, pole ID and maximum demand are needed to assess the connection request.

    Where our crew attend to perform the connection and find that the information provided is incorrect, the job will be incomplete, and new paperwork will be required which will result in a delay to the customers connection.

    This is particularly important for private underground consumer mains that run through road reserve / public land. If the required landowner approvals and BYDA drawings have not been provided, works will not proceed.

    For more information on this process, please refer to the current Service & Installation Rules and the Hub article from June 2025.

  • Non-compliant modifications of private GI poles

    There has been an increase of non-compliant holes being drilled into private GI poles, generally for the purpose of mounting the switchboard onto the pole and allowing the cables to be run down the inside of the pole and out through a hole.

    Please be aware that this modifies the pole from the manufacture’s requirements and compromises the galvanised sealing and integrity of the pole. This may also impact on the strength rating of the pole.

    TasNetworks will not connect to a modified pole that does not meet the requirements of the Service and Installation Rules.

    Section 4.3.6 - (please read the SIR in its entirety)

    • c) No holes greater than 4mm diameter on steel poles, no more than two holes in the same plane, and no holes left unsealed

    • Note: The customer mains can be run down the outside of the pole or if run down the inside of the pole, use the manufactures hole in the bottom part of the pole (approximately 500mm below the ground).

    The above clause refers to TasNetworks poles in the Service and Installation Rules but the 1st private pole that is connected to the distribution network must also comply with this clause.

    There has been an increase of non-compliant holes being drilled into private GI poles, generally for the purpose of mounting the switchboard onto the pole and allowing the cables to be run down the inside of the pole and out through a hole.

    Please be aware that this modifies the pole from the manufacture’s requirements and compromises the galvanised sealing and integrity of the pole. This may also impact on the strength rating of the pole.

    TasNetworks will not connect to a modified pole that does not meet the requirements of the Service and Installation Rules.

    Section 4.3.6 - (please read the SIR in its entirety)

    • c) No holes greater than 4mm diameter on steel poles, no more than two holes in the same plane, and no holes left unsealed

    • Note: The customer mains can be run down the outside of the pole or if run down the inside of the pole, use the manufactures hole in the bottom part of the pole (approximately 500mm below the ground).

    The above clause refers to TasNetworks poles in the Service and Installation Rules but the 1st private pole that is connected to the distribution network must also comply with this clause.

  • Revenue Reset 2029

    TasNetworks has started planning for the 2029-34 Regulatory Control Period, with customer engagement sessions kicking off in early 2026.

    We are asking members of the Electrical Industry Liaison meetings to start thinking about the services TasNetworks provide and email us any proposed changes or areas of interest to revenue.reset@tasnetworks.com.au.

    TasNetworks has started planning for the 2029-34 Regulatory Control Period, with customer engagement sessions kicking off in early 2026.

    We are asking members of the Electrical Industry Liaison meetings to start thinking about the services TasNetworks provide and email us any proposed changes or areas of interest to revenue.reset@tasnetworks.com.au.

  • TasNetworks Annual Electrical Professionals Survey – 2025 insight

    Thank you to everyone who participated in our 2025 Electrical Professionals Satisfaction Survey.

    This survey enables us to hear the voice of the industry, better understand how well we’re delivering the services you and your clients need, and any opportunities for improvement.


    What we heard:

    • 1 in every 2 electrical professionals state they are satisfied with TasNetworks’ current services and performance.
    • And while we saw a drop in overall satisfaction from 2025 and 2024 results (down 11%) – we in fact saw an uplift in satisfaction across all the specific service attributes.
    • The industry felt TasNetworks core strengths revolved around staff knowledge, responsiveness, and technical support. This was backed up by clear communications.
    • There are however suggested areas of improvement – focusing on better coordinated communications amongst various parties to align works better; a desire for improved speed and timeliness; and considering ways the digital applications and requests could be more user friendly.
    • These are all valid and insightful forms of feedback that the team will use to guide ways in which we can improve services to Electrical Professionals.
    • With the recent introduction of the Private Underground Reporting Process, TasNetworks were interested to understand how the service and guiding communications have been received by industry. Feedback included:
      • High degrees of awareness (88%) of the reporting process through Before You Dig Australia. With 2 in every 3 electrical professionals agreeing this was an important reporting function to implement.
      • Around half found the change to reporting process effective, yet some still find it difficult to navigate.

    We greatly appreciate the honesty and openness of your feedback – as this will guide our continuous improvements program to support how the industry best engages and works with TasNetworks services.

    Thank you to everyone who participated in our 2025 Electrical Professionals Satisfaction Survey.

    This survey enables us to hear the voice of the industry, better understand how well we’re delivering the services you and your clients need, and any opportunities for improvement.


    What we heard:

    • 1 in every 2 electrical professionals state they are satisfied with TasNetworks’ current services and performance.
    • And while we saw a drop in overall satisfaction from 2025 and 2024 results (down 11%) – we in fact saw an uplift in satisfaction across all the specific service attributes.
    • The industry felt TasNetworks core strengths revolved around staff knowledge, responsiveness, and technical support. This was backed up by clear communications.
    • There are however suggested areas of improvement – focusing on better coordinated communications amongst various parties to align works better; a desire for improved speed and timeliness; and considering ways the digital applications and requests could be more user friendly.
    • These are all valid and insightful forms of feedback that the team will use to guide ways in which we can improve services to Electrical Professionals.
    • With the recent introduction of the Private Underground Reporting Process, TasNetworks were interested to understand how the service and guiding communications have been received by industry. Feedback included:
      • High degrees of awareness (88%) of the reporting process through Before You Dig Australia. With 2 in every 3 electrical professionals agreeing this was an important reporting function to implement.
      • Around half found the change to reporting process effective, yet some still find it difficult to navigate.

    We greatly appreciate the honesty and openness of your feedback – as this will guide our continuous improvements program to support how the industry best engages and works with TasNetworks services.

  • Holiday Period Operations

    It's that time of year where a number of our teams are taking a well-earned break over the Christmas and New Year period.

    • Technical Advice Team - will be unavailable from 18/12/25 returning 12/01/2025.
    • Customer Service Centre, Connection Services and Fault Crew will be operating with limited resources.

    All other areas of the business will shut down from Thursday 25th December 2025 and return to usual operations on Monday 5th January 2026.

    From all of us at TasNetworks, we wish you a safe and happy holiday period.

    It's that time of year where a number of our teams are taking a well-earned break over the Christmas and New Year period.

    • Technical Advice Team - will be unavailable from 18/12/25 returning 12/01/2025.
    • Customer Service Centre, Connection Services and Fault Crew will be operating with limited resources.

    All other areas of the business will shut down from Thursday 25th December 2025 and return to usual operations on Monday 5th January 2026.

    From all of us at TasNetworks, we wish you a safe and happy holiday period.

  • TasNetworks Preferred Delivery Partner Model

    supporting image

    The Expression of Interest for the Delivery Partner closed on 14 February, with five interested parties submitting responses. The evaluation process was completed in March, and we were pleased to shortlist two suppliers to progress to the Request for Proposal (RFP) stage.

    Since then, we have held multiple collaboration sessions with the shortlisted suppliers to finalise the project scope, performance management, and efficiency targets, all aimed at delivering the best value to our customers. This process has taken longer than initially anticipated. TasNetworks has not previously tendered for a single delivery partner for the regulated program of work and anticipate

    The Expression of Interest for the Delivery Partner closed on 14 February, with five interested parties submitting responses. The evaluation process was completed in March, and we were pleased to shortlist two suppliers to progress to the Request for Proposal (RFP) stage.

    Since then, we have held multiple collaboration sessions with the shortlisted suppliers to finalise the project scope, performance management, and efficiency targets, all aimed at delivering the best value to our customers. This process has taken longer than initially anticipated. TasNetworks has not previously tendered for a single delivery partner for the regulated program of work and anticipate the new approach will realise a beneficial outcome for our enterprise, customers, and the community.

    We are pleased to announce that the RFP was officially released to the two shortlisted suppliers on 15 September. As we embark on the final stage of determining our preferred partner, we are committed to securing the best outcome and partner to deliver our program safely and with high quality.