TasNetworks' 2024-2029 revenue reset project
As a provider of electricity transmission and distribution network services in Tasmania, TasNetworks is required to submit a regulatory proposal to the Australian Energy Regulator (AER) every five years, detailing our blueprint to plan, build, operate and maintain Tasmania's electricity network and customer network charges.
This page details the activities and materials that were involved in the development of our 2024-29 proposal, which was approved by the AER in April 2024. You can read a summary of our R24 engagement program here, and the AER's final decision on our proposal here.
What is a revenue reset?
Visit our central revenue reset project page for more information about this vital process, which helps ensure consumers pay no more than necessary for safe and reliable energy.
Should you have any questions about the materials on this page, or TasNetworks' revenue reset process, please email engage@tasnetworks.com.au.
- TasNetworks Strategic Engagement Team
As a provider of electricity transmission and distribution network services in Tasmania, TasNetworks is required to submit a regulatory proposal to the Australian Energy Regulator (AER) every five years, detailing our blueprint to plan, build, operate and maintain Tasmania's electricity network and customer network charges.
This page details the activities and materials that were involved in the development of our 2024-29 proposal, which was approved by the AER in April 2024. You can read a summary of our R24 engagement program here, and the AER's final decision on our proposal here.
What is a revenue reset?
Visit our central revenue reset project page for more information about this vital process, which helps ensure consumers pay no more than necessary for safe and reliable energy.
Should you have any questions about the materials on this page, or TasNetworks' revenue reset process, please email engage@tasnetworks.com.au.
- TasNetworks Strategic Engagement Team
-
Thanks for stopping by. We have now closed this survey.
On behalf of the above Distribution Network Service Providers (DNSPs), thank you for participating in our service classification forum today.
To understand how useful you found the forum, we've created a short online survey for you to share your thoughts (2 mins).
R24 project timeline
-
Engagement Phase 1 (Nov '20 - Sep '22)
TasNetworks' 2024-2029 revenue reset project has finished this stageFocus: Research and planning
-
Engagement Phase 2 (Oct - Dec '21)
TasNetworks' 2024-2029 revenue reset project has finished this stageFocus: Capability building
-
Public consultation (Nov '21)
TasNetworks' 2024-2029 revenue reset project has finished this stageTasNetworks' Draft Customer and Stakeholder Engagement Strategy
-
Strategy published (Jan '22)
TasNetworks' 2024-2029 revenue reset project has finished this stageTasNetworks' Customer and Stakeholder Engagement Strategy
-
Engagement Phase 3 (Jan - Jul '22)
TasNetworks' 2024-2029 revenue reset project has finished this stageFocus: Deep dives into key topics
-
AER publishes draft Framework (Mar '22)
TasNetworks' 2024-2029 revenue reset project has finished this stageTasNetworks' preliminary Framework and Approach
-
AER publishes final Framework (Jul '22)
TasNetworks' 2024-2029 revenue reset project has finished this stageTasNetworks' final Framework and Approach
-
Public consultation (Jul '22)
TasNetworks' 2024-2029 revenue reset project has finished this stageTasNetworks' 2024-29 Draft Plan
-
Engagement Phase 4 (Jul-Oct '22)
TasNetworks' 2024-2029 revenue reset project has finished this stageFocus: Reporting back
-
Engagement Phase 5 (Nov '22 - Jan '23)
TasNetworks' 2024-2029 revenue reset project has finished this stageFocus: Closing the loop
-
TasNetworks regulatory submission (Jan '23)
TasNetworks' 2024-2029 revenue reset project has finished this stageCombined Proposal to the AER
-
AER Issues paper published (April 2023)
TasNetworks' 2024-2029 revenue reset project has finished this stage -
AER Draft Decision published (Sept '23)
TasNetworks' 2024-2029 revenue reset project has finished this stage -
Engagement Phase 6 (Feb-Nov '23)
TasNetworks' 2024-2029 revenue reset project has finished this stage -
TasNetworks regulatory submission (Nov '23)
TasNetworks' 2024-2029 revenue reset project has finished this stageRevised Combined Proposal to the AER
-
AER public consultation (Dec '23 - Jan '24)
TasNetworks' 2024-2029 revenue reset project has finished this stage -
AER publishes Final Decision (Apr '24)
TasNetworks' 2024-2029 revenue reset project has finished this stageTasNetworks' 2024-29 Revised Proposal
-
New regulatory control period (01 July 2024 to 30 June 2029)
TasNetworks' 2024-2029 revenue reset project is currently at this stage
Engagements + materials
-
28 November → 01 December 2023
-
28 November 2023
-
22 November 2023
Key revenue reset documents
-
AER documentation
-
TasNetworks 2024-29 Revised Proposal (Nov '23)
-
TasNetworks | Revised Proposal_FULL_6 Dec 2023
-
TasNetworks | Revised Proposal_SNAPSHOT_30Nov2023
-
TasNetworks | Revised Proposal_Tariff Structure Statement_30Nov2023
-
TasNetworks | Revised Proposal_Tariff Structure Explanatory Statement_30Nov2023
-
TasNetworks | Revised Proposal_Contingent Projects Overview report_30Nov2023
-
TasNetworks | Revised Proposal_Distribution Connection Pricing Policy_30Nov2023
-
TasNetworks |Revised Proposal_Transmission Pricing Methodology_30Nov2023
-
-
TasNetworks 2024-2029 Combined Proposal (Jan '23)
-
TasNetworks 2024-2029 Draft Plan (Aug '22)
-
TasNetworks engagement reports
-
TasNetworks | R24 Engagement Report | Phase 1 (27 May 2022)
-
TasNetworks | R24 Engagement Report | Phase 2 (27 May 2022)
-
TasNetworks | R24 Engagement report | Phase 3 (17 Jan 2023) (7.96 MB) (pdf)
-
TasNetworks | R24 engagement report | Phase 3 summary (30 Aug 2022) (83.2 KB) (pdf)
-
TasNetworks | R24 Engagement Report Phase 4 (March 2023) (5.19 MB) (pdf)
-
TasNetworks | R24 Engagement Report Phase 4 summary (March 2023).pdf (82.2 KB) (pdf)
-
TasNetworks _ R24 Engagement Report phase 5 (28 March 2023)
-
TasNetworks | R24 Engagement Report phase 5 summary (28March 2023)
-
TasNetworks R24 Engagement Report phase 6 (29 March 2024) (436 KB) (pdf)
-
TasNetworks_R24 Engagement Program Executive Summary (26 July 2024) (635 KB) (pdf)
-
-
TasNetworks engagement strategy